Thursday, April 2, 2009

April 3 - Building Update

This week has been busy with building activity. The HVAC has been changed over from the old units to 90% efficiency units. We have 4 AC units sitting on the East side. 1 is for the basement (yeah! AC in the basement), 1 is for the sanctuary, 1 is for the sanctuary overflow, and 1 is for the foyer, bathrooms, nursery, practice room (no more window units when they are finished). Pipe was buried to carry our new electrical service. We will have 600amp single phase brought to the building in the near future. Keep praying!